Waikato

Waikato

Overnight closures on SH25 at Hikuai for essential bridge maintenance

State Highway 25, south of Tairua, will be closed overnight to all traffic for 5 nights between 8pm and 6am from Sunday 19 May. This is to allow for essential maintenance and repairs to the single lane Hikuai Stream bridge, just south of Tairua.

Affected road users will need to detour via SH25, looping through Coromandel township.

While this is essential maintenance work, we do appreciate this road closure involves a lengthy detour and will be disruptive.

This work is weather dependent.

NZTA explored the option of opening the road for a short period each night to allow convoys of traffic to pass, however this would impact work progress and extend overall disruption as additional night closures would be required.

Emergency services will be accommodated if required.

  • A variety of safety improvements across the Waikato have started, these will contribute towards making the roads safer. The programme of works includes a mixture of new and modified signage, new hazard warning signs, roadside safety/barrier guard rail, road widening, improved road lines and improved road markings. It is expected there will be minimal disruption for motorists while this work is completed. The works will take place until the end of June 2024. More information.

East Waikato

  • SH25 Coromandel: Ongoing recovery works to repair damage caused by last summer’s severe weather. The road is reduced to a single lane at Ruamahuna Bay, as slip stabilisation continues. Further worksites include Te Kouma, Pumpkin Hill and Whiritoa Hill. Stop/go traffic management will be in place at these locations. More information.
  • SH25A: New signage and hazard warning signs, improved road markings and audio tactile profiles (rumble strips) are being installed along SH25A to make the road safer. This work will be completed in late May with stop/go traffic management in place.
  • SH25 Hikuai: SH25 will be closed overnight to all traffic from Sunday 19 May, for 5 nights between 8pm and 6am each night, to allow for essential maintenance and repairs to the single lane Hikuai Stream bridge, just south of Tairua. Affected road users will need to detour via SH25, looping through Coromandel township. Work includes digging out and replacing capping beams - components that span the full width of the road at each end of the bridge. Steel plates will be placed over these excavations, and a temporary speed restriction will be in place, to allow traffic to cross safely during the day. Other work being done includes resurfacing the eastern approach to the bridge and repairs to the bridge deck. This work is weather dependent, and dates may need to change if there is wet weather. More information
  • SH2 Karangahake Gorge: Work will resume next week to repair an underslip opposite Victoria Battery. Road users should allow extra time as delays can be expected. The road will usually be reduced to a single lane with stop/go traffic management and a speed restriction in place while work is being done. Work will take between 4 and 6 weeks, depending on the weather.
  • SH27 Kaihere: Work is underway to repair an underslip, this is expected to take between 4 and 6 weeks to complete depending on weather. While this work is underway the road will be reduced to a single lane with stop/go traffic management and a speed restriction in place.

Central Waikato

  • SH1 Ātiamuri: Road widening is underway for safety barrier installation, from the Waikato River bridge south to Thorpe Road. There is currently stop/go in place for asphalt works, from Monday to Friday, 8am-5pm finishing on Friday 24 May.
  • SH1 Maroa Road: Finishing works are underway on the 4.8km site where safety barriers were installed last year. There will be no traffic management for the week commencing 20 May.
  • SH1 East Taupō Arterial: Road widening continues ahead of flexible safety barrier installation, between SH5/Napier Road and the airport roundabout. One lane is open in each direction with speed restrictions in place. Completion is expected mid-2024. More information.
  • SH41 Tokaanu: Due to a washout, the road is down to one lane under temporary traffic lights, with a 30km/h temporary speed restriction in place. Works to repair the washout are due to begin in June and will take 3-4 weeks to complete.

West Waikato

  • SH1C Waikato Expressway - Te Rapa Bypass: Drivers are advised to plan ahead for ramp closures as resurfacing on the Te Rapa section of SH1C expressway continues. The northbound on and off ramps at Koura Drive will be closed until late May to allow for resurfacing on the ramps and northbound lanes. Traffic will be reduced to one lane in each direction and shifted on to the southbound lanes with speed restrictions in place. More information.
  • SH1C Cobham Drive – ramp closures: From Monday 27 May the on and off ramps at the intersection of SH1C Cobham Drive and Wairere Drive near the Hamilton Gardens will be closed from 9am to 7pm for up to 5 days. The ramps are being closed to allow for asphalt surfacing and other minor works. Traffic wanting to access Wairere Drive from the Expressway are advised to use Galloway Street and Naylor Street if heading east and Cambridge Road if heading west. The same detours apply in reverse for traffic wanting to join SH1C from Wairere Drive. In the event of bad weather further closures may be required from Tuesday 4 June.
  • SH1 Waikato Expressway - Ngāruawāhia section: Safety improvements and remedial works continue with traffic managed through the site with single lanes and 50km/h speed restriction. There will be night-time closures and a detour in place for northbound traffic 19-23 May, 7pm-5am. More information.
  • SH1 Karāpiro (Hickey Road): Construction of the fifth turnaround bay in the SH1 Cambridge to Piarere safety improvements project, just north of Hickey Road, is underway. Along with constructing the turnaround bay, we’re widening the road at the weigh station on SH1, between Hickey and Hydro Roads, and installing median and side safety barriers. Temporary traffic management is in place, including a shoulder closure. More information
  • SH1 Karāpiro: SH1 Karāpiro: Work continues on a section of SH1 between Keeley’s Reserve and Moana Roa Road, where median barrier is being installed. Motorists are advised to prepare for possible congestion when travelling through the site. Night shifts are currently occurring from 7pm to 6am, Sunday to Thursday, with stop/go traffic management in place until late May. However, due to wet weather, additional night shifts are likely to be needed this Friday 17 and Saturday 18 May under stop/go traffic management. Day works continue from Monday to Friday, with a temporary speed limit of 50km/h in place. Work is on track to be completed by late June 2024. More information
  • SH1/SH29 Piarere intersection: A key focus at present is the construction of the southern (Tīrau side) approach road. To safely accommodate this work, traffic south of the roundabout has been moved onto a newly constructed section of road adjacent to SH1. This is a short bypass road which rejoins SH1 before the intersection and continues to operate as normal. This arrangement is expected to remain in place until September 2024. Motorists are asked to drive with extra care through the site, while people adjust to the new road layout. A temporary speed limit of 60km/h will be in place around the project site to protect road workers and ensure the safety of everyone travelling through the area. More information
  • SH23 Raglan: Daytime stop/go traffic management is in place just outside Raglan, at the corner of Greenslade Road and SH23. This is to allow an embankment adjacent to the road to be stabilised and is expected to be completed by Monday 20 May. The weekday stop/go traffic management will be in place between 9am and 3pm, with delays of up to 10 minutes expected. Outside of these times and over weekends the road will be fully open, with shoulder closures and speed restrictions in place.
  • SH3 Te Kūiti: Drivers on SH3 are advised to expect delays, with work taking place to build a retaining wall and culvert on a stretch of highway between Te Kūiti and the SH3/SH4 junction. Stop/go traffic management will be in place at night, with lane shifts in place during the day. Traffic management will be in place until the end of May 2024.

North Waikato

  • SH1 Pioneer Road (North): The Pioneer Road northbound off-ramp remains closed. Motorists should continue on SH1 and exit at Pōkeno northbound off-ramp, turn around at McDonald Road and head south using Pōkeno southbound on-ramp on SH1 to get off at Pioneer Road (South). Slip repairs will be ongoing until Friday 31 May.
  • SH1 Pokeno: The installation of removeable barriers to improve network reliability and help keep traffic moving in the event of an incident or breakdown on the motorway will take place from Sunday 19 to Thursday 23 May from 9pm to 5am each night. While the work is being carried out there will be a full northbound closure between the Pokeno northbound off-ramp and Pokeno northbound on-ramp. There will also be a full southbound closure between Pokeno southbound off-ramp and Pokeno southbound on-ramp on Tuesday 28 May between 9pm and 5am.
  • SH1 Nikau Road to Bombay Interchange: From Sunday 19 to Tuesday 21 between 9pm and 5am there will be a full northbound closure with the following ramps closed: Nikau Road Northbound, Beaver Road Northbound, Mill Road northbound.
  • SH1 Hampton Downs: On Sunday 19 and Wednesday 22 May between 8pm and 5am the northbound on-ramp and off-ramps will be closed. This is to undertake streetlight maintenance. A detour will be available via Mercer or Rodda Road. There may be an increased levels of noise as the crew carry out the maintenance.
  • SH1 Dragway Road to Island Block Road: On Sunday 19 and Monday 20 May between 10pm and 5am there will be a full northbound closure, to carry out resurfacing. The Dragway Road northbound ramp will be closed.

SH1 Rangiriri interchange to Hampton Downs: On Tuesday 21 May between 8pm and 5am there will be a full northbound closure with the Te Kauwhata and Hampton Downs northbound ramps closed for line marking. A detour will be available via Te Wharepu Road, Rodda Road, Hall Road, Summertime Lane, Paddy Road and Whangamarino